The Mine Expansion

miningThis post by Mark Neasbey, a Director of the Australian Centre for Value Management, is the third in a series of posts on the role of the capital budget in infrastructure decision making. In this post Mark examines the issues facing a mine expansion.

The mining operation planned to do two things – one, expand its processing facilities to deliver increased product volumes to exacting customer specifications and two, change from road to rail transport for the whole journey to the port.  An important third aspect of importance was getting the timing to market right to optimise prices and revenue.

A design for the processing facility had been prepared as well as a proposed rail alignment and rolling stock and operating schedule, which enabled a direct loading from the processing plant to train wagons.  Existing operations relied on road transport to a rail transfer point some 40kms from the mine plant.  This needed a large workforce and truck fleet and associated scheduling activities to meet shipping schedules at the port.

In this instance the key decisions that the company executives had to make were how much disruption to supply its customers could tolerate during the weeks needed to expand the plant and what would be the reliability of the delivery program to meet the market opportunity.  Their value management study helped them to assess the options to refine both the plant design and the proposed rail arrangements in a way that minimised disruptions to the existing plant operations – so product could still flow to customers and continue to generate cash flow for the business.  This was possible with a relatively minor increase in use of capital funds in the works at the plant with the rail works staging able to occur in parallel.

Whilst ongoing operating costs were reduced and volumes (and price yield) increased there were some additional asset implications. A significant reduction in the workforce enabled a portion of the accommodation, recreation etc. facilities to be redeployed to another operation and otherwise disposed of, reducing ongoing site maintenance cost.

Concluding Comments   A budget for asset projects is expected to change during the life of the project – but why it changes and whether that is up or down is something that must be actively managed. It should not be blindly adhered to, let alone ignored.  An asset project affects operating (recurrent) costs and potential revenue as well as capital, which are also important considerations for the decision-makers.

Question for today:   What ‘take-away’ do you take away from this?

The hospital that nearly wasn’t

the-hospital-that-nearly-wasntThis post is by Mark Neasbey, a Director of the Australian Centre for Value Management.  In this post Mark presents an example of the dilemma of the different attitudes to planning budgets identified in his last post – and how they may be overcome.

A major teaching hospital complex had reached a decision point about what the project must deliver vs the projected capital cost.  Hospital facilities undergo periodic redevelopment driven by substantive changes in health care practices (models of care) and capacity to service growing populations.

Here the planning involved creating new facilities and demolishing older buildings.  The models of care and health outcome objectives were clearly defined and endorsed but were complicated by the arrangement of services across the campus and the recurrent cost constraints on the health services.  Moving functions around to create space for the new facilities was one aspect and another was inefficient service delivery arrangements which had evolved over time and which were compromised by the inflexibility of the existing facilities.

So it was not possible and not appropriate to just focus on the capital project cost.

These tensions were recognised and tested in a value management study process that worked through the schematic design, the relationships between services across the campus and the sequence and timing of moving services around and into the new facilities.  This made it clear that the space requirements and associated capital project budget exceeded the original estimate.

Question was: Should the budget be left where it was and the scope of the initial redevelopment stage reduced, or should the budget be increased to enable it to be made larger?

By focusing on the clinical outcomes and hospital operating (i.e. recurrent) costs it was clear to senior management that a change in scope for the first stage was vital.  Adding extra floor space in stage 1 enabled significant reduction in operating costs ($10m p.a.).  But the extra $30m for stage 1 also enabled the second stage to be a much lower cost development – a simpler demolition and a ‘cleaner’ new build.

Question for today:   What ‘take-away’ do you take away from this?

Should infrastructure decisions be constrained by the budget?

budget-constrainedThis post by Mark Neasbey, a director in the Australian Centre of Value Management is the first of four that looks into the role of the budget in infrastructure decision making. 

We are about to undertake a capital project for which we need a planning budget. We have chosen a figure that we think is affordable and justifiable and off we go with planning. We employ architects, engineers, cost planners and other specialists to work up a proposal.  They’re all qualified experts so we can rely upon their advice to give us a value for money solution.  Right?

But now we strike a problem.  To some the capital project’s budget figure becomes the target to realise and push beyond, because once the decision-makers see the brilliance and worth of the proposal they’ll get the extra money – that way we don’t have to compromise on anything!  Right?

For others, it’s the opposite – a barrier that must not be exceeded – the limit that has to be imposed irrespective of what compromises must be made.  We simply cannot afford to pay any more.  This is because no capital project should be seen in isolation of the whole business.  The organisation’s other priorities will also need to be appreciated so the best overall outcomes can be realised.

Both attitudes have some merit.

Our question today is:  How can they be reconciled?

Public Infrastructure – Are we still a ‘fair go’ society?

756e4a1758e0160010da073e24c32a44(1)In this post, Geoff Webb picks up on the question of infrastructure access.

The concept of ‘universal service provision’ stands in stark contrast to the ‘user pays’ model which is so often cited as a fair method of delivering services to the community, but is it?

Australians have long taken pride in being considered a fairly egalitarian society with an attitude of a fair-go for all. For many years, this was reflected in public policy and in the provision of essential infrastructure to all Australians, whether they be located in major cities and urban areas or in remote and isolated locations.

The history of telephone connection fees in Australia exemplifies the point, where actual costs for individual connections could be several orders of magnitude higher for a connection in the bush compared to connection in town, but a standard connection fee was charged for both.  The community at large was, typically, fairly accepting of the idea that service charges, as long as they seemed reasonable, paid by the high number of users in the major metropolitan centres would effectively subsidise the relatively low numbers of remote and isolated services.

While critical infrastructure ownership and operation remained in government hands, Read More →

Infrastructure decisions we make – when we don’t think we are making any!

POLICE CAR- BLUE LIGHTSToday’s post is by Mark Neasbey of the Australian Centre for Value Management

We’ve all heard the line, usually around election cycles “crime is a concern to the community, crime rates are getting worse under this government – we can do better and we’ll put more police out there…blah, blah blah”. The proposal is never costed but always described as affordable and “there’ll be no tax increases to pay for this…blah, blah, blah”.

The extra police need somewhere to work – so we need more police stations. They need vehicles to respond to incidents and do their follow-up interviews etc. So we’ll need to buy more cars for them as well. So we’ve already locked-in some infrastructure commitments just bydeciding to employ more police. Well, Well, of course, the extra police are successful in arresting more suspects – that’s what you’ve employed them to do. These additional suspects need to be brought to justice. That means more appearances before magistrates and judges. But to get there they first must have legal representation and also more prosecutors – so the Director of Public Prosecutions needs more staff and most likely also needs more offices and support facilities. So a second infrastructure impact is becoming evident. The successful arrest and presentation of suspects before the courts could mean the need to appoint more magistrates and judges to deal with the increased number of cases, which in turn could mean the need for additional court rooms and related holding cells for the suspects. So we now have a third potential commitment for additional infrastructure.

But wait – there’s more…. Read More →